If the time-slice used in the round-robin scheduling policy is more than the maximum time required to execute any process, then the policy will

(A) degenerate to shortest job first
(B) degenerate to priority scheduling
(C) degenerate to first come first serve
(D) none of the above


Answer: (C)

Explanation: RR executes processes in FCFS manner with a time slice. It this time slice becomes long enough, so that a process finishes within it, It becomes FCFS.